Site Case Study 

Installation Overview

A Crane was organised to position transformer components and associated Pipework,

Access Solutions

A MEWP (Mobile Elevating Work Platform) was deployed with IPAF – Certified operators to Safely access elevated section of the transformer.

Sealing & Preparation

Transformer was purged with nitrogen to eliminate moisture and prevent condensation. Leak checks were performed prior to oil filling. A Vacuum was established and Verified to ensure internal dryness and integrity

Image2
Image1

Commissioning

Once the oil was sealed and vacuum tested , transformer oil was pumped in under controlled conditions.

Testing

Swalek engineers conducted full commissioning tests, including insulation resistance, winding checks and functional validations

The Following Tests were Carried out:

  • SFRA (Sweep Frequency Response Analysis
  • Windings turn ratio on all taps with magnetising currents
  • Vector group check
  • Windings DC Resistance on all taps
  • Demagnetisation of the core,
  • Testing of the current Transformers.
  • C&PF Testing of the winding and the bushings
  • DFR ( Dielectric Frequency Response Analysis)
  • Insulation Resistance of Windings and Core/ Frame to earth
  • Temperture calibration of the OTI/WTI with cooling system checks
  • Tap changer operational checks
  • Panel Checks / Highlighting of the Drawings
  • Preparation of the SCT15 report and document handover